Programme and Resources

A Tender Programme That Knows Hari Raya Is Coming

Critical path on a Malaysian working calendar, with manpower, plant and materials planned from your own rates.

A Malaysian construction planner pointing at a Gantt programme with the critical path highlighted, site visible through the window
aitenderbid.com/app · Bids
Preliminary Tender ProgrammeCritical pathFinish 3 weeks before completion
Site possession
Bored piling
Pile caps, basement
Frame L1 to L38, 6-day cycle
Brickwork and plaster
M&E rough-in
Facade and windows
Finishes and fit-out
T&C, CCC
Manpower HistogramPeak 286 workers, month 14
Tower crane, 2 nos, on site month 4 to 22Hired
Aluminium formwork sets: order by week 9 for frame start week 21Lead 84 days

Programme and Resources screens: rebuilt from the live product on a sample bid. Figures are examples; the arithmetic is exact.

The Programme, Calculated Not Drawn

The AI proposes logic and durations. The server does the scheduling maths, so float and the critical path are always correct.

400

Activities per programme, linked FS, SS, FF or SF with lags

3,650

Working days of range. Weekly view to 78 weeks, then monthly

4 to 7

Day aluminium formwork cycle per floor used by the PM role

MSPDI

MS Project XML export, plus an Excel Gantt with critical path

Activity Groups

MilestonesPreliminariesSubstructureFrameEnvelopeMEPFinishesExternal WorksTesting and CommissioningCompletionInterfacesMarine PilingDredgingRevetment
A project manager on site with a tablet next to a concrete pour

Resources Planned Week by Week

Labour and plant per activity become the numbers your site team and your bank ask about.

  • Manpower and plant histograms on the busiest day of each week or month
  • Manpower and plant schedules with peak numbers and on-site dates
  • Materials call-off with needed-from and order-by dates for 10 to 25 key materials
  • Project organisation chart and key personnel with qualifications
  • Cost per line: number x working days x rate per working day

Your Own Resource Libraries

Manpower

Management, Engineers, Supervisors, Skilled Workers, Operators, General Workers. Rate per hour, day, week or month. Direct hire, subcontract or labour agency.

Machinery

Earthmoving, Lifting, Concrete, Piling, Compaction and Paving, Transport, Access and Scaffolding, Power, Pumps and Air, Survey and Testing, Small Tools. Owned or hired.

Exports

DocumentFormat
Preliminary Tender Programme, Gantt with critical path, Activities and Milestones sheetsExcel
Programme for Microsoft ProjectMS Project XML
Preliminary Construction Resource Plan with native chartsExcel
Resource Plan reportWord
Project Organisation Chart and Key PersonnelPowerPoint

Programme and Resources Questions

How is the tender programme calculated?
The Planner role writes 30 to 150 activities with durations and links. The server then runs the critical path method on a working-day calendar that includes Malaysian public holidays, with FS, SS, FF and SF links, lags and not-before dates. It calculates total and free float, the critical path, milestone targets and the finish against contract completion.
What if the programme finishes late?
The Planner must shorten the critical path honestly, for example with a faster formwork cycle or more resources, or raise a high-severity issue that tells you the completion date cannot be met as tendered.
Can I open the programme in Microsoft Project?
Yes. It exports as MS Project XML (MSPDI), and as an Excel Preliminary Tender Programme with a Gantt chart, critical path, milestones, and manpower and plant shown under the bars.
Where do resource rates come from?
From your own Manpower and Machinery libraries, up to 2,000 entries each, with rates per hour, day, week or month and the source: direct hire, subcontract or labour agency for people, owned or hired for plant. The rate is frozen on the bid line, and Use Library Rate is offered when your library rate changes.